T111 Verified field progress update

Verified field progress update

A project manager counting installed pipe runs on an unfinished upper floor

Week of Sep 21, 2026 4 of 6 milestones verified 1 milestone held Client-visible

Where each milestone on the Ridgeview Medical Office Building mechanical package stands, reported from counted quantities in the accepted daily reports and not from foreman estimates, with the one milestone held and the reason second-floor piping reads 52 percent and not 60. Prepared by Dominic Ostrowski, Ironvale Mechanical project manager, from the verified count, for the Brackenhurst Builders superintendent and the owner's representative.

The update for the week of Sep 21 carried 6 milestones. Four are verified, one is drafted and one is held. A milestone is published only when a count backs it. Held items are named here and not smoothed over.

Sample template: the firm, people, clients and figures are fictional.

Milestones at a glance

Each bar shows the verified count; the drafted milestone shows its draft figure. The held milestone shows the count of 52 percent, with the field estimate in its label.

Underslab plumbing, verified
100%
First-floor ductwork, verified
100%
Rooftop units set, verified
100%
Third-floor hangers, verified at 20 percent
20%
Controls rough-in, first floor, drafted at 35 percent, not yet verified
35%
Second-floor piping, verified count 52 percent, held (field estimate 60)
52%

The four measures behind the update

The same week's record shows four measures. Scope lines confirmed first pass are 39 of 42. Submittals answered are 14 of 18. Change events with a customer decision are 7 of 9. Closeout items accepted by Brackenhurst are 2 of 27. The status update sits beside them, so a reader sees which numbers rest on counts and which are still open.

Live example from the Dashboards app, shown with Brackenhurst Builders' demo data. Block dates move forward each week, so they can differ from the sample dates on this page.

Field estimate and verified count

For the week of Sep 21, the chart compares the foreman estimate with the count of hangers and welded joints in five areas. Four areas agree exactly. Underslab plumbing, first-floor ductwork and rooftop units read 100 percent on both measures, and third-floor hangers read 20 percent on both. Second-floor piping is the only gap: 60 percent estimated and 52 percent counted, a difference of 8 points.

Live example from the Dashboards app, shown with Brackenhurst Builders' demo data.

The six milestones and how each was verified

MilestoneStatusForeman estimateVerified countVerification source
Underslab plumbing completeVerified100%100%Accepted daily reports and the underslab pressure test record
First-floor ductwork completeVerified100%100%Accepted daily reports and the duct section count walked with the site superintendent
Rooftop units setVerified100%100%Accepted daily reports and the equipment set photos
Third-floor hangersVerified20%20%Hanger count in the accepted daily reports for Sep 21 to 25
Controls rough-in, first floorDraftedNot givenDraft 35%Draft from the daily reports; the count has not been checked yet
Second-floor pipingHeld60%52%Hangers and welded joints counted with the site superintendent on Sep 23, work order WO-3110

Percentages are the share of the milestone's counted quantity that is installed. Dates are counted to Sep 28.

The verification rule

How a milestone gets from the field to the customer
Field estimateThe foreman's view of how far along an area is. It starts the conversation and is never published on its own.
Verified countHangers, welded joints, duct sections or set equipment counted in an accepted daily report or walked with the site superintendent.
VerifiedDominic Ostrowski has checked the count against the field estimate and the two agree, or the difference is explained. Only verified milestones go in the update.
DraftedPrepared from the daily reports and waiting for a count. It is shown as a draft, with no percent claimed as verified.
HeldThe estimate and the count disagree and the difference is not yet explained. The update names the milestone and says why it is held.
PublishedSent to Brackenhurst in the weekly update, normally on Friday, after Dominic Ostrowski approves it.

Second-floor piping, held

Second-floor piping: 52 percent counted, 60 percent reported

The field reported second-floor piping at 60 percent. The count of hangers and welded joints with the site superintendent gives 52 percent. The 60 percent came from a foreman estimate, not from the counted hangers and welded joints in the daily reports.

What Ironvale did. Dominic Ostrowski published the four verified milestones and held the piping figure. What is open. Marguerite Toussaint reconciles the figure with the daily reports. The work order, WO-3110, shows Needs follow-up. Consequence. The update does not claim 60 percent, and 52 percent is the count at Sep 23, not yet the published figure. Date. The reconciled piping percentage goes in the Oct 9 update.

What the record says

Live example from the Dashboards app, shown with Brackenhurst Builders' demo data.

Look-ahead for next week

Four things happen between Oct 5 and Oct 9. The condensate pump addition, work order WO-3104, is scheduled to start on Oct 5, and the crews continue the third-floor hangers.

✓Sep 25, four verified milestones published
Oct 5, Marguerite Toussaint pulls the second-floor daily reports and sets them against the Sep 23 count
Oct 7, Dominic Ostrowski checks the reconciled percentage and the first-floor controls rough-in count
Oct 8, coordination meeting with Brackenhurst, held piping explained in person
Oct 9, update published with the reconciled piping percentage

If the reconciliation changes the 52 percent, the update says so and shows the daily reports that changed it. If it does not, the update says that too.

Prepared and reviewed
DODominic OstrowskiProject manager, Ironvale Mechanical, verifies and publishes the update
MTMarguerite ToussaintProject operations manager, Ironvale Mechanical, reconciles the piping figure
AVAnjali VenkataramanProject executive, Brackenhurst Builders, receives the update

Prepared by DO with MT, for AV and the Brackenhurst superintendent.

How to use this template

Issue this update weekly from the accepted daily reports. List each milestone with its foreman estimate, its verified count and the source of the count, publish only verified milestones, and name every held one with the reason and the date it will be settled.

VariableMeaningRequired
{{project.name}}Project and package the update coversRequired
{{progress.week_label}}Week the update coversRequired
{{progress.milestone_rows}}Milestones with status, foreman estimate, verified count and sourceRequired
{{progress.held_list}}Held milestones with the reason and the date they will be settledRequired
{{progress.verification_owner}}Person who verifies counts before publicationRequired
{{progress.look_ahead}}Steps and dates for the coming weekOptional

If a required value is missing, show Needs review in its place; never fill it with a guess. If the daily reports cannot be read, show Unavailable instead of the percentages.