Sold scope confirmation list

A mechanical contractor's estimator and foremen reviewing drawings in a site trailer

Bid accepted Aug 14, 2026 3 scope lines questioned Oldest question 16 days Client-visible

The 42 scope lines Ironvale Mechanical sold to Brackenhurst Builders for the Ridgeview Medical Office Building mechanical package, grouped by subcontract package, with the two accepted alternates, the six exclusions and the three lines still questioned in the field. Prepared by the Ironvale estimator at turnover for the Brackenhurst project manager and the Ironvale field foremen. State on Monday, September 28, 2026.

The bid accepted on Aug 14 came into project controls as 42 scope lines, 3 alternates and 6 exclusions, together with the estimate assumptions behind each line. Thirty-nine lines were confirmed on the first pass. Three are still questioned in the field. The oldest has been open for 16 days and asks who supplies the rooftop unit curbs.

Scope lines sold42Ridgeview mechanical package
Confirmed first pass39Of 42 lines
Alternates accepted2Of 3 in the bid
Oldest question16daysRooftop unit curbs

Sample template: the firm, people, clients and figures are fictional.

Scope by package

The subcontract has four packages: Rooftop units and ductwork, Hydronic piping, Plumbing and fixtures, and Controls and commissioning. The chart splits the 42 lines by package. Each bar shows the lines confirmed on the first pass and the lines the field still questions. Rooftop units and ductwork carries 2 of the 3 questions, and Plumbing and fixtures carries the third.

Live example from the Dashboards app, shown with Brackenhurst Builders' demo data. Block dates move forward each week, so they can differ from the sample dates on this page.

How many lines are confirmed

A line is confirmed when Brackenhurst and Ironvale both agree what was sold, who supplies it and which estimate assumption governs it. Confirmation means the line can go into the field briefing for the next coordination meeting.

Live example from the Dashboards app, shown with Brackenhurst Builders' demo data.

Confirmed first pass, 39 of 42 lines
93%

Scope line table

PackageScope linesConfirmed first passQuestionedField statusIronvale owner
Rooftop units and ductwork141222 questionedDominic Ostrowski
Hydronic piping12120ConfirmedRidgeview crew foreman
Plumbing and fixtures10911 questionedRidgeview crew foreman
Controls and commissioning660ConfirmedIronvale project engineer
Total42393

Days are counted to Sep 28. The three questioned lines are the only open items on this list.

Questioned linePackageDays questionedWhat the field askedNext step
Rooftop unit curbsRooftop units and ductwork16Who supplies the curbs: the estimate assumed the roofing contractor, the Brackenhurst scope matrix lists them under mechanicalAnjali Venkataraman settles it with the roofing contractor before Oct 8
Crane and rigging for the rooftop unitsRooftop units and ductwork9The estimate carries one crane day, and the scope matrix lists the crane as site-providedDominic Ostrowski checks the proposal line, then Brackenhurst confirms the crane
Domestic water heater ventingPlumbing and fixtures5The proposal prices the vent run to the roof, and the drawings note venting by othersIronvale estimator marks the proposal line, Brackenhurst confirms the drawing note

Alternates and exclusions

The bid carried three alternates. Brackenhurst accepted two of them at award.

Alternates in the bid
Alternate 1, energy recovery on the rooftop unitsAccepted. Sits in Rooftop units and ductwork.
Alternate 2, variable frequency drives on the hydronic pumpsAccepted. Sits in Hydronic piping.
Alternate 3, graphic controls workstationNot accepted. It stays out of the mechanical scope unless Brackenhurst asks for it as a change event.
The 6 exclusions that go with the 42 lines
  • Roofing, flashing and curb waterproofing
  • Electrical power wiring and equipment disconnects
  • Fire alarm and sprinkler work
  • Concrete housekeeping pads and equipment pads
  • Temporary heat and temporary ventilation
  • Hazardous material abatement

Exclusions are read before any extra work is discussed. If the field is asked to do something on this list, it goes to the project manager as a change event first.

The rooftop unit curbs

Rooftop unit curbs: questioned for 16 days

The estimate assumed the roofing contractor supplies the rooftop unit curbs. The Brackenhurst scope matrix lists them under mechanical. Both documents are in the record, and the field cannot order curbs against two answers.

What Ironvale did. Dominic Ostrowski confirmed what Ironvale sold from the proposal. What is open. Anjali Venkataraman agreed to settle the curb question with the roofing contractor. Consequence. Until the answer is recorded, the rooftop unit lines stay at 12 of 14 confirmed and the curb order and the remaining rooftop unit lines wait on the recorded answer. Date. The answer is needed before the Oct 8 coordination meeting.

I confirmed what we sold from the proposal. Whoever ends up supplying the curbs, the answer goes into the record before the crew orders or sets anything against it.

Dominic OstrowskiProject manager, Ironvale Mechanical, fictional

Confirmation steps

The package moves through four visible states. Today the package sits at handoff review, with three lines still waiting on an answer.

✓Bid accepted, Aug 14
Handoff review, 3 lines open
Scope confirmed
Project controls active
Before the Oct 8 coordination meeting
✓Confirm what was sold on the rooftop unit curbs from the proposal. Owner: Dominic Ostrowski, done
Settle the curb supply with the roofing contractor. Owner: Anjali Venkataraman, Oct 7
Confirm who provides the crane for the rooftop units. Owner: Dominic Ostrowski, Oct 7
Confirm the water heater venting note on the drawings. Owner: Ironvale estimator, Oct 7
Send the accepted alternates, exclusions and open questions to the field leads. Owner: Marguerite Toussaint, Oct 7

The field leads see the two accepted alternates, the six exclusions and every open scope question before each coordination meeting. A line moves to confirmed only when the answer is written in the record, not when it is agreed in conversation.

What the record says today

Live example from the Dashboards app, shown with Brackenhurst Builders' demo data.

Sign-off
AVAnjali VenkataramanProject executive, Brackenhurst Builders, confirms the questioned lines
DODominic OstrowskiProject manager, Ironvale Mechanical, confirms what was sold
MTMarguerite ToussaintProject operations manager, Ironvale Mechanical, routes the confirmed scope to the field

Prepared by the Ironvale estimator at turnover. Reviewed by DO MT and sent to AV for confirmation.

How to use this template

Prepare this list at turnover and refresh it after every coordination meeting. Group the sold lines by subcontract package, mark each as confirmed or questioned, and record who answers each open question and by when.

VariableMeaningRequired
{{project.name}}Project and package the list coversRequired
{{scope.package_lines}}Sold scope lines by package with first-pass and questioned countsRequired
{{scope.questioned_lines}}Lines questioned in the field, days open and next stepRequired
{{alternate.accepted_list}}Alternates in the bid and whether each was acceptedRequired
{{exclusion.bid_list}}Exclusions stated in the bidRequired
{{signoff.confirming_owner}}Client person who confirms each questioned lineRequired
{{scope.estimate_assumptions}}Estimate assumptions behind each lineOptional

If a required value is missing, show Needs review in its place; never fill it with a guess. If the record cannot be read, show Unavailable instead of the counts.