T43 Implementation kickoff plan

Implementation kickoff plan

An implementation kickoff between a software team and a clinic network

Beacon Target go-live: Nov 3, 2026 2 items blocked Week 3 of 8

The shared plan for Beacon's Clinicflow implementation: every milestone, who owns it and what needs a decision before go-live. Prepared by the Clinicflow Implementation team for Beacon's project lead, Tomas Lind, and updated weekly through go-live. Customer names, dates and figures in this template are synthetic sample data.

Kickoff goals
CustomerBeacon
VendorClinicflow
Implementation managerPriya Nair, with milestones also owned by Leo Hart
Customer project leadTomas Lind
Target go-liveNov 3, 2026 (staging complete Oct 9, production Nov 3)
PlanGrowth, 240 licensed users

Sample template: the firm, people, clients and figures are fictional, and the embedded view holds synthetic sample records.

Live example from the Dashboards app, shown with Harborline Logistics's demo data.

What we are trying to achieve

Beacon is moving 240 support and delivery staff off a legacy ticketing tool. The kickoff goal is a working staging environment by Oct 9, with user import, permission audit and template rebuild complete, so production training can start the week of Oct 12.

The live implementation plan

The table below is the shared source of truth for every customer we are currently onboarding, sorted by target date. Beacon's rows are the ones to track for this plan; other customers' rows will keep moving independently.

Before you share this page with a client

This view lists implementation milestones for every customer we are onboarding, not only Beacon. Before sending this page to Tomas Lind or anyone at Beacon, switch the embed to a saved view filtered to Customer equals Beacon, or copy this page and embed that filtered view instead.

Beacon milestones at a glance

MilestoneWorkstreamStatusOwnerTarget dateNote
Beacon admin enablementTrainingCompleteLeo HartSep 11, 2026Admins can manage users and templates
Beacon user importDataBlockedPriya NairSep 21, 2026HR group list not delivered
Historical importDataCustomer actionPriya NairSep 26, 2026Waiting on a clean export from the legacy tool
Permission auditConfigurationPlannedLeo HartOct 6, 2026Needs the HR group list first
Beacon template rebuildConfigurationConfiguringPriya NairOct 9, 2026Template inventory already reviewed with Tomas

Phases

✓Discovery and admin setup
Data migration
Configuration and permissions
Integration testing
Training
Go-live

Who owns what

MilestoneResponsibleAccountableConsultedInformed
Beacon user importPriya Nair, ClinicflowPriya NairTomas Lind and Beacon HRLeo Hart
Historical importPriya Nair, ClinicflowPriya NairBeacon legacy tool adminTomas Lind
Permission auditLeo Hart, ClinicflowLeo HartTomas LindBeacon support managers
Template rebuildPriya Nair, ClinicflowPriya NairBeacon workflow leadsTomas Lind
Training rolloutLeo Hart, ClinicflowLeo HartBeacon support managersAll Beacon end users

What is blocking us

Beacon user import is blocked

The 240-account user import needs the HR group list so accounts land in the correct groups on creation. Beacon's operations director role changed in August, and the new director has not yet signed off the group names submitted in July. We need: Tomas Lind to get written sign-off, or a revised list, by Sep 26. Impact if it slips past Sep 26: the permission audit and template rebuild both wait on this import, which pushes the Oct 9 staging milestone and puts the Nov 3 go-live at risk.

Historical import is customer-dependent

The two-year project history import needs a clean export from Beacon's legacy tool. This is scheduled but not started; it does not block staging, only the decision on whether history is visible from day one of go-live.

Kickoff checklist

Before staging opens, Oct 9
✓Kickoff call held with Tomas Lind and the Beacon support leadership team
✓Environments provisioned: sandbox, staging, production
✓Admin enablement session delivered
HR group list signed off by Beacon's operations director
240 user accounts imported with correct groups
Clean legacy export received for historical import
Permission audit scheduled with Beacon support managers

We are ready to move as soon as our new operations director signs off the group list. That is the one thing on our side holding this up.

Tomas LindProject Lead, Beacon, fictional
PNPriya NairImplementation Manager, Clinicflow
TLTomas LindProject Lead, Beacon

Confidence in the Nov 3 go-live

Confidence in hitting Nov 3★★★★★3/5

Three out of five while the user import is blocked. This moves to four once the HR group list is signed off, because every other milestone is on or ahead of schedule.

How to use this template

Duplicate this page once per customer at kickoff. Replace the values below; if a required value is missing, show Needs review rather than guessing a date or owner.

VariableMeaningRequired
{{customer.name}}Customer the implementation coversRequired
{{customer.project_lead}}Named contact on the customer sideRequired
{{implementation.manager}}Vendor-side implementation ownerRequired
{{implementation.target_golive}}Agreed go-live dateRequired
{{milestone.blocked_dependency}}What is blocking any milestone in Blocked status, and who owns clearing itRequired when a milestone is blocked
{{milestone.target_date}}Target date per milestone, pulled from the trackerOptional

Before sharing: filter the embedded view to this customer only, and confirm every blocked or customer-action milestone names an owner and a date.